Developers planned 86 GW of new capacity for 2026, but by August each technology—solar, wind, batteries, and natural gas—was about a quarter behind its planned capacity.
Problem
Developers’ 2026 capacity plans for solar, wind, batteries, and natural gas were overestimated, with each technology falling short by roughly a quarter of its projected 2026 capacity by August.
Outcome
All four technologies lost about a quarter of their 2026 capacity plans by August, with natural gas slipping most and almost none of its projects dropping out. Combustion turbines were further along than combined‑cycle units.
Workflow
- 1. Downloaded EIA December 2025 monthly inventory via Catalyst Cooperative’s PUDL.
- 2. Filtered generators that were online in 2026 or planned for a 2026 month.
- 3. Updated the inventory to the August 2026 report.
- 4. Calculated percentage of planned capacity lost for each technology.
- 5. Analyzed gas project shifts to 2027 or later and identified projects that slipped or were removed.
- 6. Compared combustion turbine and combined‑cycle online status.
- 7. Cross‑checked raw records of two plants (Trumbull Energy Center and Orange County Advanced Power Station) with EIA data.
- 8. Published findings and predictions before running the job.
Evidence
Each technology lost about a quarter of its plan.
Gas slipped more than solar or batteries, and almost none of it dropped out.
Combustion turbines are further along than combined cycle by August (48.4% online against 27.4%).
The raw records of the two plants EIA named match its article.