Solar, wind, batteries and gas each lost about a quarter of their 2026 plan by August
Описание и применение
Разработчики планировали добавить 86 ГВт новой мощности к 2026 году, но к августу каждая технология (солнечная, ветровая, аккумуляторная и природный газ) отставала примерно на четверть от запланированного объёма.
Задача
Developers’ 2026 capacity plans for solar, wind, batteries, and natural gas were overestimated, with each technology falling short by roughly a quarter of its projected 2026 capacity by August.
Результат
All four technologies lost about a quarter of their 2026 capacity plans by August, with natural gas slipping most and almost none of its projects dropping out. Combustion turbines were further along than combined‑cycle units.
Рабочий процесс
- 1. Downloaded EIA December 2025 monthly inventory via Catalyst Cooperative’s PUDL.
- 2. Filtered generators that were online in 2026 or planned for a 2026 month.
- 3. Updated the inventory to the August 2026 report.
- 4. Calculated percentage of planned capacity lost for each technology.
- 5. Analyzed gas project shifts to 2027 or later and identified projects that slipped or were removed.
- 6. Compared combustion turbine and combined‑cycle online status.
- 7. Cross‑checked raw records of two plants (Trumbull Energy Center and Orange County Advanced Power Station) with EIA data.
- 8. Published findings and predictions before running the job.
Доказательства
Each technology lost about a quarter of its plan.
Gas slipped more than solar or batteries, and almost none of it dropped out.
Combustion turbines are further along than combined cycle by August (48.4% online against 27.4%).
The raw records of the two plants EIA named match its article.